Description
Supply of one EPR turbine-island mechanical procurement package. The reference covers construction materials, manufacturing services or linked equipment within the EPR infrastructure model.
Nuclear electricity
Reference product Procurement mechanical TI EPR CH
Stable dataset identity
procurement-mechanical-ti-epr
1.0.1Published inventory
Process description and catalog context. View scientific metadata
Supply of one EPR turbine-island mechanical procurement package. The reference covers construction materials, manufacturing services or linked equipment within the EPR infrastructure model.
Classification, keywords, bookmarks and download counts.
Classification path: Energy > Electricity > Nuclear electricity
Log in to bookmarkSource documentation, background profiles and references.
Scientific journal publication
Simons, A., Bauer, C. (2012). Life cycle assessment of the European pressurized reactor and the influence of different fuel cycle strategies. Proceedings of the Institution of Mechanical Engineers, Part A: Journal of Power and Energy 226(3), 427–444. https://doi.org/10.1177/0957650912440549
Inventory changes relative to source: Not assessed
Equivalence to the original source inventory has not been established.
These are the stored source profiles for this version. Foreground methodology is recorded in Scientific metadata.
Missing exchange uncertainty generation: Not requested
Representativeness scores use a 1–5 scale when provided. Lower scores indicate a closer fit to the modeled technology, geography, or time period.
Precalculated screening profile
Results per unit, using UVEK 2025 and the ecoinvent 3.10 biosphere. Exchange rows are shaded from green to red by relative contribution to the selected indicator.
8 of 9 non-zero exchanges were scored (89%). Unmapped exchanges are excluded, not treated as zero.
This screening result uses Brightpath mappings from the source background to UVEK 2025; mapped suppliers are not claims of scientific equivalence.
Profile uvek-2025-ef-v3-1-4e70d56a85b1 · artifact
4e70d56a85b1 · calculated
2026-11-23 19:11 UTC. These screening results do not replace a reviewed comparative LCA.
Outputs
| Exchange | Reference / categories | Amount | Unit | Metadata | Climate change contribution |
|---|---|---|---|---|---|
|
procurement mechanical TI EPR
CH
|
Procurement mechanical TI EPR
Axpo NH 5b / year technologies
|
1
|
unit | Reference flow |
Inputs
| Exchange | Reference / categories | Amount | Unit | Metadata | Climate change contribution |
|---|---|---|---|---|---|
|
condenser EPR
RER
|
Condenser EPR
Materials/fuels
|
1
|
unit |
54476.7
mol H+-Eq / unit
18.4% of total
9.5805e+06
kg CO2-Eq / unit
18.5% of total
3.7134e+07
CTUe / unit
18.1% of total
3590.81
kg P-Eq / unit
16.8% of total
9431.16
kg N-Eq / unit
18.4% of total
100215
mol N-Eq / unit
18.4% of total
0.190968
CTUh / unit
19.0% of total
1.00672
CTUh / unit
18.7% of total
2.5848e+06
kBq U235-Eq / unit
19.1% of total
4.6942e+07
dimensionless / unit
18.6% of total
0.154645
kg CFC-11-Eq / unit
17.4% of total
0.749417
disease incidence / unit
18.9% of total
32972.1
kg NMVOC-Eq / unit
18.5% of total
1.3007e+08
MJ, net calorific value / unit
18.9% of total
316.441
kg Sb-Eq / unit
18.4% of total
2.8507e+06
m3 world Eq deprived / unit
18.6% of total
|
|
|
Cross over pipes & pipes HPT to separator-reheater EPR
Materials/fuels
|
1
|
unit |
3437.22
mol H+-Eq / unit
1.2% of total
629030
kg CO2-Eq / unit
1.2% of total
2.5384e+06
CTUe / unit
1.2% of total
234.917
kg P-Eq / unit
1.1% of total
593.867
kg N-Eq / unit
1.2% of total
6303.07
mol N-Eq / unit
1.2% of total
0.0118502
CTUh / unit
1.2% of total
0.0628367
CTUh / unit
1.2% of total
155083
kBq U235-Eq / unit
1.1% of total
2.9935e+06
dimensionless / unit
1.2% of total
0.0116273
kg CFC-11-Eq / unit
1.3% of total
0.0468923
disease incidence / unit
1.2% of total
2040.81
kg NMVOC-Eq / unit
1.1% of total
7.9661e+06
MJ, net calorific value / unit
1.2% of total
19.9929
kg Sb-Eq / unit
1.2% of total
165672
m3 world Eq deprived / unit
1.1% of total
|
||
|
generator EPR
RER
|
Generator EPR
Materials/fuels
|
1
|
unit | Not scored — no BAFU factor | |
|
Moisture separator-reheater HTP-LPT EPR
Materials/fuels
|
2
|
unit |
33081.4
mol H+-Eq / unit
11.2% of total
5.8570e+06
kg CO2-Eq / unit
11.3% of total
2.2863e+07
CTUe / unit
11.2% of total
2193.95
kg P-Eq / unit
10.2% of total
5725.1
kg N-Eq / unit
11.2% of total
60822.9
mol N-Eq / unit
11.2% of total
0.115649
CTUh / unit
11.5% of total
0.610246
CTUh / unit
11.3% of total
1.5565e+06
kBq U235-Eq / unit
11.5% of total
2.8556e+07
dimensionless / unit
11.3% of total
0.0969021
kg CFC-11-Eq / unit
10.9% of total
0.454449
disease incidence / unit
11.4% of total
19957.7
kg NMVOC-Eq / unit
11.2% of total
7.8590e+07
MJ, net calorific value / unit
11.4% of total
192.208
kg Sb-Eq / unit
11.2% of total
1.7080e+06
m3 world Eq deprived / unit
11.1% of total
|
||
|
Pipes HPT to reheater stage 2 EPR
Materials/fuels
|
1
|
unit |
749.346
mol H+-Eq / unit
0.3% of total
137131
kg CO2-Eq / unit
0.3% of total
553363
CTUe / unit
0.3% of total
51.213
kg P-Eq / unit
0.2% of total
129.468
kg N-Eq / unit
0.3% of total
1374.13
mol N-Eq / unit
0.3% of total
0.00258349
CTUh / unit
0.3% of total
0.0136991
CTUh / unit
0.3% of total
33808.5
kBq U235-Eq / unit
0.3% of total
652605
dimensionless / unit
0.3% of total
0.00253463
kg CFC-11-Eq / unit
0.3% of total
0.0102229
disease incidence / unit
0.3% of total
444.914
kg NMVOC-Eq / unit
0.3% of total
1.7367e+06
MJ, net calorific value / unit
0.3% of total
4.35865
kg Sb-Eq / unit
0.3% of total
36117.8
m3 world Eq deprived / unit
0.2% of total
|
||
|
Pipes, valves TI EPR
Materials/fuels
|
1
|
unit |
91243.9
mol H+-Eq / unit
30.8% of total
1.5656e+07
kg CO2-Eq / unit
30.2% of total
6.5063e+07
CTUe / unit
31.8% of total
7995.41
kg P-Eq / unit
37.3% of total
15083.2
kg N-Eq / unit
29.5% of total
160601
mol N-Eq / unit
29.5% of total
0.292437
CTUh / unit
29.2% of total
1.62858
CTUh / unit
30.3% of total
3.8267e+06
kBq U235-Eq / unit
28.3% of total
7.4972e+07
dimensionless / unit
29.6% of total
0.293785
kg CFC-11-Eq / unit
33.0% of total
1.16976
disease incidence / unit
29.4% of total
51626.3
kg NMVOC-Eq / unit
29.0% of total
1.9681e+08
MJ, net calorific value / unit
28.6% of total
540.452
kg Sb-Eq / unit
31.4% of total
4.0995e+06
m3 world Eq deprived / unit
26.7% of total
|
||
|
turbine EPR
RER
|
Turbine EPR
Materials/fuels
|
1
|
unit |
110895
mol H+-Eq / unit
37.4% of total
1.9443e+07
kg CO2-Eq / unit
37.5% of total
7.5120e+07
CTUe / unit
36.7% of total
7289.45
kg P-Eq / unit
34.0% of total
19201.4
kg N-Eq / unit
37.5% of total
204050
mol N-Eq / unit
37.5% of total
0.389222
CTUh / unit
38.8% of total
2.05096
CTUh / unit
38.1% of total
5.2812e+06
kBq U235-Eq / unit
39.1% of total
9.5482e+07
dimensionless / unit
37.7% of total
0.31029
kg CFC-11-Eq / unit
34.8% of total
1.52649
disease incidence / unit
38.4% of total
67215
kg NMVOC-Eq / unit
37.8% of total
2.6535e+08
MJ, net calorific value / unit
38.5% of total
644.092
kg Sb-Eq / unit
37.5% of total
5.8372e+06
m3 world Eq deprived / unit
38.0% of total
|
|
|
market for transport, freight, lorry, unspecified
RER
|
transport, freight, lorry, unspecified
Materials/fuels
|
2.52e+06
|
ton kilometer |
1993.5
mol H+-Eq / unit
0.7% of total
476117
kg CO2-Eq / unit
0.9% of total
1.3546e+06
CTUe / unit
0.7% of total
45.3175
kg P-Eq / unit
0.2% of total
819.848
kg N-Eq / unit
1.6% of total
8519.56
mol N-Eq / unit
1.6% of total
0.000167221
CTUh / unit
0.0% of total
0.00369673
CTUh / unit
0.1% of total
54992.8
kBq U235-Eq / unit
0.4% of total
2.8137e+06
dimensionless / unit
1.1% of total
0.0177231
kg CFC-11-Eq / unit
2.0% of total
0.014713
disease incidence / unit
0.4% of total
3041.18
kg NMVOC-Eq / unit
1.7% of total
6.9015e+06
MJ, net calorific value / unit
1.0% of total
1.11576
kg Sb-Eq / unit
0.1% of total
552087
m3 world Eq deprived / unit
3.6% of total
BAFU:2025
|
|
|
market for transport, freight, lorry, unspecified
RER
|
transport, freight, lorry, unspecified
Materials/fuels
|
5.10e+05
|
ton kilometer |
403.446
mol H+-Eq / unit
0.1% of total
96357
kg CO2-Eq / unit
0.2% of total
274152
CTUe / unit
0.1% of total
9.17139
kg P-Eq / unit
0.0% of total
165.922
kg N-Eq / unit
0.3% of total
1724.2
mol N-Eq / unit
0.3% of total
3.3842e-05
CTUh / unit
0.0% of total
0.000748147
CTUh / unit
0.0% of total
11129.5
kBq U235-Eq / unit
0.1% of total
569442
dimensionless / unit
0.2% of total
0.00358681
kg CFC-11-Eq / unit
0.4% of total
0.00297762
disease incidence / unit
0.1% of total
615.477
kg NMVOC-Eq / unit
0.3% of total
1.3967e+06
MJ, net calorific value / unit
0.2% of total
0.225808
kg Sb-Eq / unit
0.0% of total
111732
m3 world Eq deprived / unit
0.7% of total
BAFU:2025
|
Read-only definitions preserved with this inventory version. Values are supplied by the source; CLIC does not evaluate formulas or recalculate exchange amounts and impact scores from them.
No parameter definitions were supplied with this inventory snapshot.
Reuse and provenance
Add this version to your basket, inspect original uploads, or reuse it in your LCA software.
Original source files are currently unavailable, but you can still add this version to your basket for generated package export.
Published versions are immutable and remain available.
Oldest to newest. Arrows show recorded revision links; each node describes the change introduced by that version.
First published inventory; no earlier version is available for comparison.
SupersededActivity and product names for procurement mechanical TI EPR now use consistent catalogue spelling across the inventory and its supplier references. The physical recipe…
Published · Viewing · Latest| Version | Published | Reason for this version | Link |
|---|---|---|---|
| Version 1.0.1 | 2026-11-03 | Activity and product names for procurement mechanical TI EPR now use consistent catalogue spelling across the inventory and its supplier references. The physical recipe is unchanged. | Current view |
| Version 1.0.0 Superseded | Published 2026-07-15 | First published inventory; no earlier version is available for comparison. | Open version |
Activity and product names for procurement mechanical TI EPR now use consistent catalogue spelling across the inventory and its supplier references. The physical recipe is unchanged.
Source: https://doi.org/10.1177/0957650912440549.
Declared foreground licence: CC-BY-4.0. Source publications and external supplier inventories retain their own terms.
Activity and product names for procurement mechanical TI EPR now use consistent catalogue spelling across the inventory and its supplier references. The physical recipe is unchanged.
This comparison is permanently visible with the published version so users can assess every detected change before reuse.
| Exchange / scope | Field | Previous value | Revised value | Reason |
|---|---|---|---|---|
| condenser EPR (technosphere / RER / unit) | Name | Condenser EPR | condenser EPR | Activity and product names now follow consistent catalogue spelling, so the intended inventory and its supplier references remain identifiable. |
| cross over pipes & pipes HPT to separator-reheater EPR (technosphere / RER / unit) | Name | Cross over pipes & pipes HPT to separator-reheater EPR | cross over pipes & pipes HPT to separator-reheater EPR | |
| generator EPR (technosphere / RER / unit) | Name | Generator EPR | generator EPR | |
| moisture separator-reheater HTP-LPT EPR (technosphere / RER / unit) | Name | Moisture separator-reheater HTP-LPT EPR | moisture separator-reheater HTP-LPT EPR | |
| pipes HPT to reheater stage 2 EPR (technosphere / RER / unit) | Name | Pipes HPT to reheater stage 2 EPR | pipes HPT to reheater stage 2 EPR | |
| pipes, valves TI EPR (technosphere / RER / unit) | Name | Pipes, valves TI EPR | pipes, valves TI EPR | |
| turbine EPR (technosphere / RER / unit) | Name | Turbine EPR | turbine EPR |
| Exchange / scope | Field | Previous value | Revised value | Reason |
|---|---|---|---|---|
| procurement mechanical TI EPR (production / CH / unit) | Name | Procurement mechanical TI EPR | procurement mechanical TI EPR | Activity and product names now follow consistent catalogue spelling, so the intended inventory and its supplier references remain identifiable. |
| Exchange / scope | Field | Previous value | Revised value | Reason |
|---|---|---|---|---|
| Version metadata | Description | Simons A, Bauer C. Life cycle assessment of the Evolutionary Power Reactor (EPR) and the influence of different fuel cycle strategies. Proceedings of the Institution of Mechanical Engineers, Part A: Journal of Power and Energy. 2012;226(3):427-444. doi:10.1177/0957650912440549 | Supply of one EPR turbine-island mechanical procurement package. The reference covers construction materials, manufacturing services or linked equipment within the EPR infrastructure model. | No explanation was recorded for this change. |
| Version metadata | Methodology and allocation explanation | The source is a 2012 prospective assessment of Swiss/French EPRs in 2030, using mixed-vintage fuel-cycle and infrastructure data. Table 4 distinguishes CH 1500 MWe from FR 1530 MWe; the common 1500-MWe description is not valid for the French scenario. The regional RER copy is not a separately tabulated source scenario. The paper's normal-operation boundaries exclude nuclear accidents. Equipment membership is traced only through unambiguous declared foreground links; underlying bills of materials and supplier/biosphere adaptations remain incompletely verified. | Source scenario and ancestry Simons and Bauer (2012) assess prospective Swiss/French European pressurized reactors in 2030. The whole-study functional unit is 1 kWh at the plant busbar, distinct from this component or construction reference. The source distinguishes CH 1,500 MWe from FR 1,530 MWe, uses a 60-year operating life and different cooling/fuel-cycle choices, and combines mixed-vintage background data. The RER copy is not a separately tabulated source scenario. These are historical scenario assumptions rather than current operating-fleet observations or a common component measurement year. Earlier inventories are acknowledged to Roberto Dones and Roth et al. (2009). |
|
| Version metadata | Source | Simons, A., & Bauer, C. Life cycle assessment of the Evolutionary Power Reactor (EPR) and the influence of different fuel cycle strategies. Proceedings of the Institution of Mechanical Engineers, Part A: Journal of Power and Energy. 2012;226(3):427-444. https://doi.org/10.1177/0957650912440549 | Simons, A., Bauer, C. (2012). Life cycle assessment of the European pressurized reactor and the influence of different fuel cycle strategies. Proceedings of the Institution of Mechanical Engineers, Part A: Journal of Power and Energy 226(3), 427–444. https://doi.org/10.1177/0957650912440549 | |
| Version metadata | Contributors, publications, projects and supporting evidence | Funding: 1. Project: Url: https://doi.org/10.1177/0957650912440549 Funding: 1. Project: Name: Life cycle assessment of the European pressurized reactor and the influence of different fuel cycle strategies Funding: 1. Project: Acronym: Not set Funding: 1. Project: Relation: source_study Funding: 1. Project: Grant identifier: Not set Funding: 1. Organization: Ror: Not set Funding: 1. Organization: Url: Not set Funding: 1. Organization: Name: Axpo Holding AG Funding: 1. Award identifier: Not set Evidence: 1. Origin: editor_verification Evidence: 1. Target field: data_origins Evidence: 1. Qualification: Exact documented origins; no claim that every flow is measured. Evidence: 1. Source location: source Evidence: 1. Source reference: Existing published CLIC inventory documentation Evidence: 2. Origin: editor_verification Evidence: 2. Target field: included_life_cycle_stages Evidence: 2. Qualification: Only the documented supplied function; component recipes do not inherit the full parent lifecycle. Manufacturing rejects do not imply product end of life. Evidence: 2. Source location: name Evidence: 2. Source reference: Existing published CLIC inventory documentation Evidence: 3. Origin: editor_verification Evidence: 3. Target field: intended_application Evidence: 3. Qualification: Source-linked modelling context; no 2030 component year or measured manufacturer inventory is inferred. Evidence: 3. Source location: source Evidence: 3. Source reference: Existing published CLIC inventory documentation Evidence: 4. Origin: editor_verification Evidence: 4. Target field: publications Evidence: 4. Qualification: Bibliographic details refer to this explicitly cited DOI. Existing citation text is retained, including any additional sources. Publication year does not establish the inventory reference year; publication authors are not assigned as inventory compilers. Evidence: 4. Source location: DOI registration: title, publication dates and byline Evidence: 4. Source reference: https://api.crossref.org/works/10.1177%2F0957650912440549 Evidence: 5. Origin: editor_verification Evidence: 5. Target field: publications Evidence: 5. Qualification: Canonical institutional identity only. Preserve historical declared spelling, departments, attribution and funding relationships; identity verification alone does not verify an award or its scope. Evidence: 5. Source location: Organization identity and registered names Evidence: 5. Source reference: https://api.ror.org/v2/organizations/03eh3y714 Evidence: 6. Origin: editor_verification Evidence: 6. Target field: publications Evidence: 6. Qualification: Canonical primary and legacy citations are aligned without changing freeform source, inventory source text or inventory contributors. Publication year is not a measurement/reference year. EPR underlying inventories are acknowledged to Roberto Dones and Roth et al. (2009); component quantities are not all printed in the 2012 article. Preserve each declared source role and historical affiliation. Evidence: 6. Source location: Original paper/SI byline; pinned DOI registration and institutional identity evidence Evidence: 6. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 7. Origin: editor_verification Evidence: 7. Target field: methodology_notes Evidence: 7. Qualification: Distinguish electricity, dedicated plant equipment and fuel-cycle supply roles. Only CH/FR electricity nodes receive the explicit 2030 model year. No component measurement year, capacity factor, numeric TRL or accident-risk result is inferred. Evidence: 7. Source location: Table 4, source scope and acknowledgements; foreground equipment paths Evidence: 7. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 8. Origin: editor_verification Evidence: 8. Target field: funding Evidence: 8. Qualification: Axpo Holding AG funded the cited study. The project declaration is labelled by the paper title with relation source_study; no formal grant/acronym is invented and no funding of the CLIC adaptation is inferred. Evidence: 8. Source location: Source funding statement immediately before acknowledgements Evidence: 8. Source reference: https://doi.org/10.1177/0957650912440549 Projects: 1. Url: https://doi.org/10.1177/0957650912440549 Projects: 1. Name: Life cycle assessment of the European pressurized reactor and the influence of different fuel cycle strategies Projects: 1. Acronym: Not set Projects: 1. Relation: source_study Projects: 1. Grant identifier: Not set Publications: 1. Doi: 10.1177/0957650912440549 Publications: 1. Url: https://doi.org/10.1177/0957650912440549 Publications: 1. Title: Life cycle assessment of the European pressurized reactor and the influence of different fuel cycle strategies Publications: 1. Scientific authors: 1. Name: Andrew Simons Publications: 1. Scientific authors: 1. Orcid: Not set Publications: 1. Scientific authors: 1. Affiliations: 1. Ror: https://ror.org/03eh3y714 Publications: 1. Scientific authors: 1. Affiliations: 1. Url: Not set Publications: 1. Scientific authors: 1. Affiliations: 1. Name: Laboratory for Energy Systems Analysis, Paul Scherrer Institute, Villigen PSI, Switzerland Publications: 1. Scientific authors: 2. Name: Christian Bauer Publications: 1. Scientific authors: 2. Orcid: 0000-0002-1083-9200 Publications: 1. Scientific authors: 2. Affiliations: 1. Ror: https://ror.org/03eh3y714 Publications: 1. Scientific authors: 2. Affiliations: 1. Url: Not set Publications: 1. Scientific authors: 2. Affiliations: 1. Name: Laboratory for Energy Systems Analysis, Paul Scherrer Institute, Villigen PSI, Switzerland Publications: 1. Citation: Simons, A., Bauer, C. (2012). Life cycle assessment of the European pressurized reactor and the influence of different fuel cycle strategies. Proceedings of the Institution of Mechanical Engineers, Part A: Journal of Power and Energy 226(3), 427–444. https://doi.org/10.1177/0957650912440549 Publications: 1. Relation: primary_source Publications: 1. Source type: scientific_journal Publications: 1. Publication year: 2012 |
Funding: 1. Project: Url: https://doi.org/10.1177/0957650912440549 Funding: 1. Project: Name: Life cycle assessment of the European pressurized reactor and the influence of different fuel cycle strategies Funding: 1. Project: Acronym: Not set Funding: 1. Project: Relation: source_study Funding: 1. Project: Grant identifier: Not set Funding: 1. Organization: Ror: Not set Funding: 1. Organization: Url: Not set Funding: 1. Organization: Name: Axpo Holding AG Funding: 1. Award identifier: Not set Evidence: 1. Origin: editor_verification Evidence: 1. Target field: data_origins Evidence: 1. Qualification: Exact documented origins; no claim that every flow is measured. Evidence: 1. Source location: source Evidence: 1. Source reference: Existing published CLIC inventory documentation Evidence: 2. Origin: editor_verification Evidence: 2. Target field: included_life_cycle_stages Evidence: 2. Qualification: Only the documented supplied function; component recipes do not inherit the full parent lifecycle. Manufacturing rejects do not imply product end of life. Evidence: 2. Source location: name Evidence: 2. Source reference: Existing published CLIC inventory documentation Evidence: 3. Origin: editor_verification Evidence: 3. Target field: intended_application Evidence: 3. Qualification: Source-linked modelling context; no 2030 component year or measured manufacturer inventory is inferred. Evidence: 3. Source location: source Evidence: 3. Source reference: Existing published CLIC inventory documentation Evidence: 4. Origin: editor_verification Evidence: 4. Target field: publications Evidence: 4. Qualification: Bibliographic details refer to this explicitly cited DOI. Existing citation text is retained, including any additional sources. Publication year does not establish the inventory reference year; publication authors are not assigned as inventory compilers. Evidence: 4. Source location: DOI registration: title, publication dates and byline Evidence: 4. Source reference: https://api.crossref.org/works/10.1177%2F0957650912440549 Evidence: 5. Origin: editor_verification Evidence: 5. Target field: publications Evidence: 5. Qualification: Canonical institutional identity only. Preserve historical declared spelling, departments, attribution and funding relationships; identity verification alone does not verify an award or its scope. Evidence: 5. Source location: Organization identity and registered names Evidence: 5. Source reference: https://api.ror.org/v2/organizations/03eh3y714 Evidence: 6. Origin: editor_verification Evidence: 6. Target field: publications Evidence: 6. Qualification: Canonical primary and legacy citations are aligned without changing freeform source, inventory source text or inventory contributors. Publication year is not a measurement/reference year. EPR underlying inventories are acknowledged to Roberto Dones and Roth et al. (2009); component quantities are not all printed in the 2012 article. Preserve each declared source role and historical affiliation. Evidence: 6. Source location: Original paper/SI byline; pinned DOI registration and institutional identity evidence Evidence: 6. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 7. Origin: editor_verification Evidence: 7. Target field: methodology_notes Evidence: 7. Qualification: Distinguish electricity, dedicated plant equipment and fuel-cycle supply roles. Only CH/FR electricity nodes receive the explicit 2030 model year. No component measurement year, capacity factor, numeric TRL or accident-risk result is inferred. Evidence: 7. Source location: Table 4, source scope and acknowledgements; foreground equipment paths Evidence: 7. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 8. Origin: editor_verification Evidence: 8. Target field: funding Evidence: 8. Qualification: Axpo Holding AG funded the cited study. The project declaration is labelled by the paper title with relation source_study; no formal grant/acronym is invented and no funding of the CLIC adaptation is inferred. Evidence: 8. Source location: Source funding statement immediately before acknowledgements Evidence: 8. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 9. Origin: editor_verification Evidence: 9. Target field: technology_description Evidence: 9. Qualification: Technical-characterisation review TC-2223. Design capacity: Unspecified. Basis: Mechanical procurement assembly does not independently specify steam or power capacity. Evidence classification: guarded source table and reference boundary review. Confidence: high for retained source assumption not measured performance. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 9. Source location: fields/design_capacity; source Tables4–5 and exact component scope Evidence: 9. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 10. Origin: editor_verification Evidence: 10. Target field: technology_description Evidence: 10. Qualification: Technical-characterisation review TC-2223. Design capacity unit: Unspecified. Basis: Mechanical procurement assembly does not independently specify steam or power capacity. Evidence classification: guarded source table and reference boundary review. Confidence: high for retained source assumption not measured performance. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 10. Source location: fields/design_capacity_unit; source Tables4–5 and exact component scope Evidence: 10. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 11. Origin: editor_verification Evidence: 11. Target field: technology_description Evidence: 11. Qualification: Technical-characterisation review TC-2223. Capacity factor (%): Unspecified. Basis: Mechanical procurement assembly does not independently specify steam or power capacity. Evidence classification: guarded source table and reference boundary review. Confidence: high for retained source assumption not measured performance. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 11. Source location: fields/capacity_factor_percent; source Tables4–5 and exact component scope Evidence: 11. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 12. Origin: editor_verification Evidence: 12. Target field: technology_description Evidence: 12. Qualification: Technical-characterisation review TC-2223. Annual production volume: Unspecified. Basis: Mechanical procurement assembly does not independently specify steam or power capacity. Evidence classification: guarded source table and reference boundary review. Confidence: scope or denominator unresolved. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 12. Source location: fields/annual_production_volume; source Tables4–5 and exact component scope Evidence: 12. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 13. Origin: editor_verification Evidence: 13. Target field: technology_description Evidence: 13. Qualification: Technical-characterisation review TC-2223. Annual production volume unit: Unspecified. Basis: Mechanical procurement assembly does not independently specify steam or power capacity. Evidence classification: guarded source table and reference boundary review. Confidence: high for retained source assumption not measured performance. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 13. Source location: fields/annual_production_volume_unit; source Tables4–5 and exact component scope Evidence: 13. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 14. Origin: editor_verification Evidence: 14. Target field: technology_description Evidence: 14. Qualification: Technical-characterisation review TC-2223. Annual production volume year: Unspecified. Basis: Mechanical procurement assembly does not independently specify steam or power capacity. Evidence classification: guarded source table and reference boundary review. Confidence: high for retained source assumption not measured performance. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 14. Source location: fields/annual_production_volume_year; source Tables4–5 and exact component scope Evidence: 14. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 15. Origin: editor_verification Evidence: 15. Target field: technology_description Evidence: 15. Qualification: Technical-characterisation review TC-2223. Plant or represented-asset lifetime (years): Unspecified. Basis: Mechanical procurement assembly does not independently specify steam or power capacity. Evidence classification: guarded source table and reference boundary review. Confidence: scope or denominator unresolved. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 15. Source location: fields/plant_lifetime_years; source Tables4–5 and exact component scope Evidence: 15. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 16. Origin: editor_verification Evidence: 16. Target field: technology_description Evidence: 16. Qualification: Technical-characterisation review TC-2223. Commercial maturity stage: early_commercial. Basis: Retain the legacy early-commercial assessment as EPR supply-chain/scenario context, not independent proof of this exact component's market stage. The 2012 prospective model and a source inventory package do not establish present-day deployment or procurement qualification. Evidence classification: source scenario and exact process boundary assessment. Confidence: medium curator judgement with explicit scope limits. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 16. Source location: Study scope and Tables4–5; exact retained EPR component/fuel-service review Evidence: 16. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 17. Origin: editor_verification Evidence: 17. Target field: technology_description Evidence: 17. Qualification: Technical-characterisation review TC-2223. Technology readiness level: 8. Basis: Retain the legacy EPR-context curator rating with an explicit component-scope limitation. It is not a publisher-assigned score for every cable, fuel-cycle or procurement helper and does not certify the material bill or nuclear qualification. Exact own-component readiness remains a source-scope question. Evidence classification: source scenario and exact process boundary assessment. Confidence: medium curator judgement with explicit scope limits. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 17. Source location: Study scope and Tables4–5; exact retained EPR component/fuel-service review Evidence: 17. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 18. Origin: editor_verification Evidence: 18. Target field: technology_description Evidence: 18. Qualification: Technical-characterisation review TC-2223. Technological representativeness: 4. Basis: The paper models prospective 2030 EPR pathways with mixed-vintage background information. Exact component inventories contain material/processing proxies and incompletely verified source bills. They meet the prospective/proxy representation category4, rather than a claim of observed industrial operating data for each item. Evidence classification: source scenario and exact process boundary assessment. Confidence: medium curator judgement with explicit scope limits. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 18. Source location: Study scope and Tables4–5; exact retained EPR component/fuel-service review Evidence: 18. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 19. Origin: editor_verification Evidence: 19. Target field: technology_description Evidence: 19. Qualification: Technical-characterisation review TC-2223. Geographical representativeness: 1. Basis: RER is an archived regional proxy and is not a separately tabulated scenario in the source paper; category3 reflects generic regional transfer. CH/FR labels retain their source scenario matching, without claiming a measured manufacturing site or operating reactor sample for each component. Evidence classification: source scenario and exact process boundary assessment. Confidence: medium curator judgement with explicit scope limits. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 19. Source location: Study scope and Tables4–5; exact retained EPR component/fuel-service review Evidence: 19. Source reference: https://doi.org/10.1177/0957650912440549 Evidence: 20. Origin: editor_verification Evidence: 20. Target field: technology_description Evidence: 20. Qualification: Technical-characterisation review TC-2223. Temporal representativeness: 4. Basis: The 2030 date is a scenario horizon in a 2012 prospective study, not a future measurement year or a refresh of underlying manufacturing inputs. The retained scenario/proxy inventories meet category4 for prospective or stale representation; source publication and plant-life assumptions do not supply measurement coverage. Evidence classification: source scenario and exact process boundary assessment. Confidence: medium curator judgement with explicit scope limits. A retained model value is not a measured observation or industrial certification. Source-specific assumptions and detailed technical parameters accompany this plan. Evidence: 20. Source location: Study scope and Tables4–5; exact retained EPR component/fuel-service review Evidence: 20. Source reference: https://doi.org/10.1177/0957650912440549 Projects: 1. Url: https://doi.org/10.1177/0957650912440549 Projects: 1. Name: Life cycle assessment of the European pressurized reactor and the influence of different fuel cycle strategies Projects: 1. Acronym: Not set Projects: 1. Relation: source_study Projects: 1. Grant identifier: Not set Publications: 1. Doi: 10.1177/0957650912440549 Publications: 1. Url: https://doi.org/10.1177/0957650912440549 Publications: 1. Title: Life cycle assessment of the European pressurized reactor and the influence of different fuel cycle strategies Publications: 1. Scientific authors: 1. Name: Andrew Simons Publications: 1. Scientific authors: 1. Orcid: Not set Publications: 1. Scientific authors: 1. Affiliations: 1. Ror: https://ror.org/03eh3y714 Publications: 1. Scientific authors: 1. Affiliations: 1. Url: Not set Publications: 1. Scientific authors: 1. Affiliations: 1. Name: Laboratory for Energy Systems Analysis, Paul Scherrer Institute, Villigen PSI, Switzerland Publications: 1. Scientific authors: 2. Name: Christian Bauer Publications: 1. Scientific authors: 2. Orcid: 0000-0002-1083-9200 Publications: 1. Scientific authors: 2. Affiliations: 1. Ror: https://ror.org/03eh3y714 Publications: 1. Scientific authors: 2. Affiliations: 1. Url: Not set Publications: 1. Scientific authors: 2. Affiliations: 1. Name: Laboratory for Energy Systems Analysis, Paul Scherrer Institute, Villigen PSI, Switzerland Publications: 1. Citation: Simons, A., Bauer, C. (2012). Life cycle assessment of the European pressurized reactor and the influence of different fuel cycle strategies. Proceedings of the Institution of Mechanical Engineers, Part A: Journal of Power and Energy 226(3), 427–444. https://doi.org/10.1177/0957650912440549 Publications: 1. Relation: primary_source Publications: 1. Source type: scientific_journal Publications: 1. Publication year: 2012 |
|
| Version metadata | Technological representativeness | 2 | 4 | |
| Version metadata | Temporal representativeness | 3 | 4 | |
| Version metadata | Intended application | Foreground modelling of the declared EPR hardware, fuel-cycle or electricity-production configuration. | Component-level turbine-island mechanical procurement provision within a consistently assembled EPR construction model, retaining its declared unit and current supplier/reference mappings. | Apply reviewed discovery metadata and change explanations from the curated release. |
| Version metadata | System boundary | Not set | The recorded turbine-island mechanical procurement material/service supply and linked manufacturing or procurement inputs per declared reference. Whole-plant operation, fuel use, electricity generation and decommissioning are separate. | |
| Version metadata | Technology description | Not set | The package links the condenser, crossover and reheater piping, generator, separator-reheaters, pipe/valve package and turbine, with additional road freight. The linked construction modules and added freight retain their respective boundaries; the assembly does not establish an additional operating process. | |
| Version metadata | Limitations on use | Not set | Evidence and boundary limits The paper supports the source model context; its aggregate technology table does not independently verify each detailed component bill, supplier/biosphere mapping or uncertainty. Equipment membership is traced through unambiguous declared foreground links. The source scope covers normal operation and excludes nuclear accidents. It does not supply an accident-risk result or establish present equipment ratings. Axpo support belongs to the source study, not automatically to later CLIC adaptations. Recorded scoped correction checks do not establish a complete amendment history. |
|
| Version metadata | Name | Procurement mechanical TI EPR | procurement mechanical TI EPR | Activity and product names now follow consistent catalogue spelling, so the intended inventory and its supplier references remain identifiable. |
Publication route
This inventory was restored from a public CLIC archive. Its original publication route is Curator-led bulk import; private review and workflow records were not transferred.
Use this form to report a problem with this dataset or version. To report an individual public comment, use “Report this comment” beside that comment. To propose better numerical inventory data, use “Suggest an inventory improvement” in the inventory section.
Log in to report content